Summary 

DelaControl delivered a full control system obsolescence upgrade for an industrial waste incineration facility, replacing an end-of-life Siemens S7-300 platform with a current S7-1500 F-CPU, migrating the existing Step 7 5.5 PLC software to TIA Portal, and rebuilding the supervisory SCADA system from Wonderware InTouch to Siemens WinCC. The scope covered hardware build, full documentation, factory acceptance testing, site installation, commissioning, and operator training.

Challenge

The facility's incinerator control system was built around an obsolete  Siemens S7-300 PLC platform, including ET200 remote I/O devices,  presenting a long-term supportability risk.

The supervisory SCADA  system was running on Wonderware InTouch, and the customer required  both the control platform and the SCADA to be brought up to a modern,  maintainable standard while preserving the existing control philosophy  documented in the functional description.

Solution

DelaControl designed and built new control system backplates housing the  replacement Siemens S7-1500 F-CPU and associated I/O modules. The  Siemens PLC hardware, IPCs, and operator screens were free-issued by  Siemens and housed in enclosures supplied by DelaControl. All  consumables, panel metalwork, terminals (Weidmueller), low-voltage  control gear, circuit protection, and 24V power supplies were  Siemens-branded components selected to DelaControl's standard  specification.

Site installation involved two industrial  electricians working over ten days to disconnect, remove the old  backplate, install the new backplate, and re-terminate all field cables.  Field cable liaison with existing sub-contractors was also included.

The  existing Step 7 5.5 PLC software was fully migrated to a TIA Portal  S7-1500 project. Any control logic changes arising from the platform  migration were captured in a dedicated PLC code migration report. The  SCADA system was rewritten from scratch on Siemens WinCC, covering  thirteen operator screens including plant overview, process area pages,  trends, reports, logs, and alarms.

The delivery package included a  full drawing pack (general arrangements and schematics in AutoCAD  Inventor and AutoCAD Electrical/Eplan), thermal calculations using  Rittal Therm software, a Declaration of Conformity to LVD and EMC  directives, a functional test schedule agreed with the client, factory  acceptance testing, site commissioning (two control systems engineers  over fifteen calendar days), and two full-day operator training sessions  at DelaControl's Bristol facility.

Key Facts

• Platform migration from obsolete Siemens S7-300 (Step 7 5.5) to S7-1500 F-CPU on TIA Portal
• SCADA rebuilt from Wonderware InTouch to Siemens WinCC — 13 operator screens in scope
• Site installation: 2 industrial electricians on site for 10 days (24 man days total)
• Site commissioning: 2 control systems engineers, 15 calendar days, 37 man days total
• Factory acceptance test conducted with end client and system integrator present
• 2 full-day operator training sessions included, hosted at DelaControl's Bristol facility
•  Documentation package included thermal calculations, Declaration of  Conformity, FAT schedule and certificate, detail design specification,  software design specification, and operator manual
• Security  requirement: only British passport holders assigned to the project; all  project data held in director-level password-protected encrypted storage